We are almost there!!!! This past week we have have several things go forward. The kitchen cabinets and the counter top is now all in, looks awsome. The flooring in the kitchen was some what of a trial but after two weeks of work they are looking great. The trim work on the second floor is done, stair railing is in, painting upstairs is also very close to being done just a little touch up. The lights are all in and working. We are waiting on the trim work on the first floor to be finished, should be some time this weekend and then the hard woods will go down. We will then have painting and some stain work to be done. It is looking like we should be done 1st week in Jan. We are slowly moving things to the basement which is nice not to have to do it all at once. We will be listing our home with a realtor this week and hope to have it sold by end of January but we will see.