Saturday, October 1, 2011

*** Internals ****

A lot of work has been going on inside.  They have been able to get the living room framed in and it was weird to see it in it's new form.  Most of the plumbing is in, heating is done, and the electrical should be finished and ready for inspection on Monday.  Once inspections are done on Monday they can start on insulation and then the drywall.  Our cabinets have been ordered and will be in mid Nov. (not moving in end of Oct - surprise).  Once drywall is up we get to work.  We are going to do some painting and tile work. (any experts want to help we pay well in dinners).  We will have hardwoods down stiars, and carpet up.  I have been trying to get hardwood to go up the stairs but boy is it expensive.  So things are moving along. I am looking forward for the siding to go on.  We still do not have colors picked out - any thoughts?